Data centres must store two days’ water supply, use alternative sources

Featured

Data centres must keep at least two days’ worth of water in storage, give priority to alternative water sources and pay for any extra infrastructure needed to serve them, the Dewan Rakyat was told. The conditions sit inside the guidelines applied by the National Water Services Commission, the New Straits Times reported on 18 Nov.

Water consumption by the sector in Selangor, Johor and Negri Sembilan is projected to reach 445.04 million litres a day by 2030, according to Deputy Minister Datuk Seri Abdul Rahman Mohamad.

“The priority of ensuring water supply for existing customers continues to be upheld,” he told the House while winding up the debate on the ministry’s allocation under the Supply Bill 2027, in an account carried by BernamaBiz.

Reclaimed water is already carrying part of the load. About 19.5 million litres a day of recycled water from four sewage treatment plants in Selangor and Johor is being supplied to data centres, trimming their draw on treated water meant for households.

A written parliamentary reply by Deputy Prime Minister Fadillah Yusof, carried by Free Malaysia Today in July, put operating consumption at 28.68 million litres a day as of January, about 51.4 per cent of the 55.83 million litres a day those centres demand.

The matter was raised by Yeo Bee Yin (PH-Puchong) and Muhammad Bakhtiar Wan Chik (PH-Balik Pulau), who pressed the ministry on the water and electricity consumption of the fast-growing industry. Balik Pulau is a parliamentary seat on Penang island.

On electricity, Abdul Rahman said supply planning rests on the meeting of the committee on electricity supply planning and tariffs on 11 Nov. The reserve margin for 2027 to 2035 is projected at between 24 and 27 per cent, a level the government considers enough to support data centre growth.

Demand-side measures for heavy energy users, data centres included, have been identified to defend that margin. Connected load charge rates were tiered to curb excessive capacity bookings, and the ultra-high-voltage tariff structure that took effect on 1 July 2025 applies to operators drawing above 50 kilovolts. The ministry also noted Yeo’s proposal to publish the committee’s report.

In Johor, data centres are also being pushed to run on treated water drawn from polluted rivers rather than potable supply.

The Dewan Rakyat then approved RM5.33 billion in operating and development expenditure for the ministry under Budget 2027, after a debate involving 32 members of Parliament.

Look here 👇

Join our Channels on Whatsapp & Telegram
Like our Facebook Page 👉🏻 PenangToday
Join our Facebook Group 👉🏻 PenangToday Community
Follow our Instagram 👉🏻 @penangtoday
We are on TikTok 👉🏻 @penang2day
Gotta cover LinkedIn 👉🏻 PenangToday
Our Threads be like 👉🏻 @penangtoday
Get on our X 👉🏻 @penang2day
Here's our Youtube 👉🏻 PenangToday

Related

Latest

Popular