The first package of the Juru-Sungai Dua traffic dispersal project is 54.61 per cent complete, highway concessionaire PLUS Malaysia Bhd said in a statement on 17 Nov, The Star reported.
Physical progress stood at that level as at 8 Nov, Bernama put it in its Bahasa Malaysia report on the same statement, which the concessionaire described as positive progress for the project.
Package One covers improvement works to the access ramps at the East-West Interchange Roundabout and the construction of a new bridge along Jalan Tun Hussein Onn. “These works aim to increase road capacity and improve traffic flow in the surrounding area,” PLUS said.
That leaves 45.39 per cent of the package outstanding, with the remaining ramp and bridge works still to be built. The statement gave no completion date for Package One.
Packages Two to Five are at the final tendering stage, with the works planned in phases. A final tendering stage means bids for the work have been called and the concessionaire is closing out the process before contracts are awarded. Packages Two and Five cover construction between the Juru toll plaza and the Juru lay-by, and between the Samagagah lay-by and the Sungai Dua toll plaza. Packages Three and Four cover elevated sections and interchanges between the Juru lay-by and the Samagagah lay-by.
The 17.4km project connects the Juru toll plaza and the Sungai Dua toll plaza. It is estimated to cost RM3 billion and, in the New Straits Times account, is designed to serve more than 200,000 road users a day across three main districts.
PLUS expects 30 per cent of traffic to move to the new direct Juru-Sungai Dua route once the corridor is finished, cutting peak-hour travel time from one hour to 20 minutes.
A lay-by is a marked stopping area on the shoulder of a highway, separate from the main carriageway. The five packages split the corridor into stages. The two end sections run to the toll plazas at Juru and Sungai Dua, while the middle stretch between the two lay-bys carries the elevated works and interchanges.
The scheme is known in Malay as Projek Penyuraian Trafik Juru-Sungai Dua (PTJSD), the name used in the concessionaire’s Bahasa Malaysia statement. The statement on the later packages carried no tender closing date and no start date for Packages Two to Five.
“Upon completion, the project is expected to enhance highway capacity, improve traffic flow and deliver long-term benefits to highway users and the surrounding communities,” PLUS said.